Community Center Parking Lot Paving Schedule

On Monday, September 11, the first half of the lot will be completed. See photo above of area marked in RED.
 
On Tuesday, September 12, the second half of the lot will be completed. The circulation road will remain open to provide access to the Community Center. Community Center access off of Shingle Creek will be closed. See photo above of area marked in BLUE.

The Community Center lot will be open for softball on Monday and Tuesday evenings.
On Wednesday, September 13, the Community Center lot will be striped early morning.