Road Closure - Firehouse Park Reconstruction Area

2018 Firehouse Park Area Reconstruction Project
Roads Closed
Beginning Today, June 25, 2018

 
Attached is a map of the road closure areas affected by the 2018 Firehouse Park Area Reconstruction Project. The indicated streets will be closed and open only to immediate residents within the construction area, their guests and service providers such as sanitation pick up, deliveries vehicles, post office vehicles, etc. School buses must use alternate routes and stay out of the closure areas. Please make arrangements for alternate pick up and drop off locations for your students. It is crucial that all school buses use alternate routes and stay out of the construction area.

Stage 1 roads will remain closed to through traffic until substantial completion of that stage. Stage 1 substantial completion is scheduled for approximately the end of July 2018.
Stage 2 roads will remain to through traffic until substantial completion of that stage. Stage 2 substantial completion is scheduled for approximately the end of August 2018.
Stage 3A roads (east of Dupont) will be closed to through traffic starting on Monday June 26, 2018 until substantial completion of that stage.  Stage 3 substantial completion is scheduled for Mid-October 2018.
  
For any questions or concerns regarding this matter please contact 763-569-3340 or publicworks@ci.brooklyn-center.mn.us. Thank you.
Brooklyn Center Public Works/Engineering

 