Brooklyn Boulevard Corridor Project - Phase I
Brooklyn Center, in coordination with Hennepin County, is preparing for reconstruction and streetscape improvements on a 1.3-mile segment of Brooklyn Center between 49th Avenue and Bass Lake Road (County Road 10). This project is scheduled to be constructed in 2018.


Project Details
The proposed reconstruction and streetscape improvements will improve roadway safety, enhance traffic operations, reduce access points and provide improved bicycle and pedestrian facilities. The project will enhance bicycle and pedestrian travel by adding a trail, improving sidewalks, transit stops, adding streetscaping and landscaping and improving the functionality of intersections with modified turn lanes.
                       
The City completed the Brooklyn Boulevard Corridor Study in 2013 to guide the reconstruction and redevelopment of this corridor. This project consists of Project Nos. 1, 2, 4, 5, 6, 6A and 7 as identified within the Brooklyn Boulevard Corridor Study. Note that Project No. 6 has been revised to be a full reconstruction rather than a mill and overlay.

Federal funding through the Surface Transportation Program has been awarded to the City and Hennepin County for this project and the regional Transportation Improvement Plan is expected to be amended to include this project. The local partnership and proportions are to be determined in the future but are anticipated to include Hennepin County, Three Rivers Park District and City funding.

                       
Contact Information
Please contact the Project Manager/Engineer for all project coordination issue and information.
  • Mike Albers, Project Manager/Engineer: 763-569-3340 or


Project History                                              
  • July 2013 - The City completed the Brooklyn Boulevard Corridor Study to guide the reconstruction and redevelopment of this corridor.
  • November 2014 - The City applied for federal funding through the Surface Transportation Program to fund a portion of this project.
  • May 2015 - Federal funding through the Surface Transportation Program was awarded to the City and Hennepin County for this project in the amount of $7,420,000 and the remaining project costs are to be funded from local funding as part of the required cost share. Local funding partnerships and proportions are continuing to be formulated and are anticipated to include Hennepin County, City of Brooklyn Center and other possible funding from local jurisdictions.
  • May 9, 2016 - City Council approved a resolution establishing this project and directed staff to proceed with the preliminary design, environmental documentation, easement acquisition and final design work for the Brooklyn Boulevard Corridor Project Phase 1 (49th Avenue to Bass Lake Road).
  • June 3, 2016 - City staff in cooperation with Hennepin County solicited proposals for preliminary design work on the Brooklyn Boulevard Corridor Project Phase 1.
  • August 8, 2016 - City Council approved a resolution authorizing execution of a Professional Services Agreement with SRF Consulting Group, Inc. for the design work on the Brooklyn Boulevard Corridor Project Phase 1.   
           

Preliminary Project Schedule                       
August 2016 thorough March 2018 - Preliminary and Final Design Work

April 2018
- Anticipated Bid Opening

Spring 2018
- Start Construction

Fall 2019
- End Construction

                   




               









                           

               







                                                                   
               